Power Infrastructure Upgrade Enables Future Growth for Computer Parts Manufacturing Facility - San Jose, CA

Category: Computer Parts Manufacturing 

Total Area: 115,000 ft² 

Services Provided: Electrical Engineering 

Completion Date: 2025 

Owner: Confidential 

Contractor: RC Power  

Subcontractor: PASE (Structural & Civil) 

Project Description

To support expanding production needs at a 115,000 ft² computer parts manufacturing facility, Pragmatic PE delivered the engineering and design of a new medium voltage-to-low voltage transformer and switchgear system. The upgrade ensures scalable capacity, safe operation, and cost-effective implementation for long-term facility growth. 

Scope of Work

  • Conducted detailed site verification, including assessment of the existing 21.7kV primary distribution system and underground infrastructure. 

  • Identified and coordinated available feeder circuits and vault connections to accommodate a new 2500 kVA transformer and 4000A main switchboard (MSB). 

  • Developed calculations and engineered drawings for the new transformer installation, switchgear integration, and future load considerations. 

  • Reviewed vendor transformer and switchboard submittals, provided technical revisions, and ensured compliance with California codes. 

  • Created trenching and feeder routing plans in coordination with structural and civil subcontractor PASE. 

  • Sized medium voltage feeders, loadbreak junction bars, and elbow connectors to optimize reliability and safety. 

Challenges & Solutions 

Challenge: Limited access to underground distribution feeders for splicing. 

Solution: Designed a splice solution using loadbreak junction bars and elbows, minimizing disruption and future risk. 

Challenge: Ensuring new capacity without overloading existing switchgear. 

Solution: Calculated load capacity for existing switches to verify available space for new and future loads. 

Results & Impact 

  • Delivered engineered drawings for city submission, ensuring code compliance and streamlined approvals. 

  • Provided a cost-effective, constructible design that minimized trenching and site disruptions. 

  • Enhanced electrical reliability and capacity to meet both current and future facility demand. 

  • Enabled seamless contractor coordination, accelerating project execution and reducing field change orders. 

Next
Next

Electrical Fault Study & Switchgear Design for High-Density Data Center - San Jose, CA